General area –220kV 2019.12
General area: Mongolia, the new construction of 110k double loops on the user side of Erlianhot microgrid project. Wire:JL/G1A-240/30.Ground wire: OPGW-24B1-80. The total length of the line is 11KM, Total quantity:angle steel tower is 35 sets. Total weight : 483 tons. The order is signed in September 2019, and the production time is 22 days. It has been put into operation normally in early March 2020.



Project name:Mongolia 110kV substation project
Tower No.:N43 hoisting
Date:2019.12.14

Project name:Mongolia 110kV substation project
Tower No.:N43 hoisting
Date:2019.12.14

Project name:Mongolia 110kV substation project
Tower No.:N27 hoisting
Date:2019.12.13